White House Ballroom Project Estimated at $600 Million, Taxpayer Funds Cover Majority

US President Donald Trump’s new ballroom in the East Wing of the White House has been estimated at a total cost of $600 million, with over half of that figure coming from taxpayer funds.

Internal accounting documents indicate a significant increase in construction costs for the project, which was originally scoped to be completed by March 2026. The latest estimates, received by White House officials between July 2025 and early 2026, show the budget has risen substantially.

According to Clark Construction—the contractor responsible for the East Wing project—on March 2, the projected cost had increased to $600 million. The funding breakdown includes $293 million intended for private sponsors, $155 million allocated to the Secret Service, $149 million from the White House Military Directorate, and $3 million from the Executive Residence—all of which would be funded by taxpayers.

During a press conference on March 2, Trump noted that construction noise was causing significant disruptions for First Lady Melania Trump. On May 19, he announced plans for a six-story underground bunker beneath the ballroom, integrated with the main structure to include sniper positions on its flat roof, bulletproof glass, bomb shelters, a military hospital, and specialized military facilities. Trump stated that construction was being carried out using private donations and was proceeding as scheduled, calling it “his gift to the United States.”